Chinese New Year 2027: when to order machined parts from China
If a new machined part needs a first-article approval, the order has to reach the Chinese shop by the end of November to be finished before Chinese New Year 2027. A repeat part with an approved drawing can wait until about 7 December. Anything ordered after that, plan for delivery in March.
The festival falls on Saturday 6 February 2027, eleven days earlier than in 2026. The date that decides your parts comes weeks before that. Yijin Solution, a CNC shop in China, says factories close for 10 to 15 days and start winding down 3 to 4 weeks before the holiday. That puts the last safe finishing date for a production batch at about 9 January.
How do you get from 9 January back to November?
The table counts back using Yijin's own planning ranges. Plan on the slow column: the run-up to the shutdown is a shop's busiest time of year.
| Stage | Fast case | Slow case |
|---|---|---|
| Production batch finished and inspected | 9 Jan | 9 Jan |
| Production release (2 to 4 weeks of machining, plus 2 to 5 days of anodising or plating) | 24 Dec | 7 Dec |
| First article approved by you (3 to 7 days to machine, 2 to 5 days to finish, 2 to 4 days by express, plus 3 to 7 days for your own measurement) | by 24 Dec | by 7 Dec |
| First-article order placed | 14 Dec | 14 Nov |
The slow-case date has already passed, so the end of November is the latest date that still leaves some margin, and none for a drawing query. Yijin notes that when a drawing goes back for confirmation, "the schedule pauses until the revised requirement is approved." A complete drawing saves that time. Six lines to send with an RFQ covers what it needs.
A repeat part skips the first article, so it only needs the production release date: about 7 December in the slow case. Shops' own notices agree. For the 2024 festival (10 February), RapidDirect told customers to place time-sensitive orders before Christmas. For 2023 (22 January), it said that from 28 December the lead time on new orders would be counted from 1 February, when its factory reopened. The same 25-day gap lands on 12 January in 2027.
Why March, and not just after the holiday?
Because reopening is not the same as full output. Yijin says factories "take further weeks to return to full output." HLH Rapid, another Chinese shop, warns that many suppliers may not be back to full production for more than a month. The ODM Group adds that factories come back to a backlog of unfinished orders, and a January order joins the back of it. HLH also warns that quality can slip after the restart, so don't waive the inspection on the first batch.
Which dates should you get from the shop in writing?
The ODM Group's 2027 guide notes that China's official holiday schedule was not yet announced, and that material suppliers, subcontractors and inspection providers "may all operate on different schedules." Ask for five dates:
- The last day a new order still gets a pre-holiday lead time. This is the date RapidDirect published. After it, the clock starts at reopening.
- The finishing subcontractor's closing date. Anodising and plating often go to a separate shop, and Yijin notes that finishing runs to its own queue, which is longer at peak times. If the parts need masking, the masking note has to be on the drawing now, not added in January.
- When the first article will be measured, and when the report reaches you.
- The last day goods leave the factory. Yijin gives 3 to 7 days for air freight and 3 to 5 weeks for sea freight, so parts finished on 9 January and sent by sea arrive between the end of January and mid-February.
- The reopening date, and when the shop expects full capacity.
What if the dates don't work?
Split the order. Release what the shop can finish by early January, and have the rest made by a shop that does not close for the festival. Fictiv, which uses factories in several countries, told customers who needed parts during the 2026 holiday to use its India, Mexico or US production. If a February or March date won't do, send the drawing to Vesprr Workshop with the quantity, material and finish, and the date the parts are due. The quote will say whether that date can be met.
Sources
- China CNC machining lead times, Yijin Solution: lead-time ranges, closure and wind-down.
- RapidDirect 2023 Chinese New Year holiday notice and Notice for Chinese New Year holiday 2024, RapidDirect: closures and cut-offs.
- 2025 Chinese New Year manufacturing: planning for the shutdown, HLH Rapid: capacity and quality after the holiday.
- China factory closures for New Year 2027: essential planning guide, The ODM Group.
- Chinese New Year 2026: how the holiday impacts manufacturing capacity, Fictiv.
- SMTCL VMC0656e 5-axis machining center, TurnOnTheNight, CC BY-SA 4.0, via Wikimedia Commons (header photo).
- Earlier on Vesprr: Chinese New Year 2027: when your hand-tool order is due.